UF’s current federally negotiated F&A Rate Agreement is available HERE.
All sponsored projects must follow the University’s Facilities & Administrative Cost Policy found at F&A Policy and F&A Directives and Procedures.
Project budgets should include all costs required to accomplish the objectives in the proposal or agreement. These costs are itemized as either:
- Direct costs (salary, fringe benefits, supplies, travel, etc.)
- Facilities and Administrative (F&A) costs incurred for sponsored programs administration and compliance, purchasing, accounting, library services, and building custodial services, depreciation, and utilities.
F&A costs cannot easily be allocated to individual projects, therefore sponsors require that they are budgeted and collected as a percentage of a project’s direct cost. When developing a contract or grant budget, use the appropriate rate below.
***Each award is subject to only ONE rate for the life of the award. The rate will be determined by how the majority of activity is performed under the project (i.e. off-campus, in an REC, or for a particular activity – Research, Other Sponsored Activity, or Instruction), and that rate will apply to the entire award. “Life” means for the competitive segment approved by the sponsor at the time of the initial award.
Negotiated Rates
| Sponsor | Type of Project Activity/Contract | Rate on MTDC (effective 7/1/2025) | Rate on MTDC (prior rates) | ||
|---|---|---|---|---|---|
| On-campus | Off-campus3 | On-campus | Off-campus3 | ||
| Sponsors without a pre-approved exemption (below) | Research | 53.5% | 26% | 52.5% | 26% |
| IFAS AREC1 – Research activities | 36.5% | 24% | 34.1% | 26% | |
| Other Sponsored Activity | 30% | 20% | 32.6% | 26% | |
| Instruction | 45% | 26% | 47.5% | 26% | |
| Scripps | 69.5% | 26% | 93.2% | ||
| Department of Defense Contracts | Research Contract or Subcontract2 | 56% | 28.5% | 54.5% | 28% |
1 Agriculture Research and Education Centers (AREC) and Florida Medical Entomology Lab within the Institute of Food and Agricultural Sciences. See: https://ifas.ufl.edu/maps/ for details.
2 If the project will be funded as a grant or cooperative agreement, then the rate used for on-campus research should be 53.5% MTDC. The DoD rate of 56% MTDC should be used for DoD procurement contracts governed by Federal Acquisition Regulations (FARs) and DoD other transaction agreement/other transaction authority (OTA).
- If the proposal is being submitted via UFIRST SF424/Grants.gov, the 53.5% F&A rate should be used.
3 The off-campus rate should be applied if the activity is conducted in any buildings that are not owned and maintained by UF and which rent is directly allocated to the project. Off-campus F&A can only be charged to projects where rent (which may be in the form of janitorial services, building maintenance, etc.) is directly charged to the project.
- Travel costs, field work and Institute of Food and Agricultural Sciences Research & Education Centers do not qualify for the off campus rate.
Last updated 6/25/26